The California Independent System Operator (CaISO), which manages the majority of the state's power grid, has approved five new transmission projects that the agency says are crucial to the state's renewable energy future. The five projects, part of a transmission plan that could cost around $1.7 billion, were green-lighted by the CaISO's Board of Supervisors on Wednesday.

The five projects:


  • The Sycamore-Peñasquitos 230-kilovolt line near Poway in San Diego County, scheduled for completion in 2017 at a cost of up to $221 million;
  • A rerouting of Southern California Edison's 500 kilovolt Eldorado-Lugo line, which now enters California from Nevada near the hamlet of Nipton in San Bernardino County -- slated for completion in 2020 at a cost of $36 million;
  • Equipment upgrades on the Eldorado-Lugo line, scheduled for 2016 at a cost of $121 million;
  • Upgrading the 230 kilovolt line between Pacific Gas & Electric's (PG&E's) substations at Warnerville (near Hetch Hetchy) and Bellota (near Escalon), scheduled for completion in 2017 at a cost of $28million, and;
  • A similar upgrade to the 115 kilovolt line between PG&E's Wilson and Le Grand substations in Merced County. This would be completed in 2020 and cost $15 million.

The CaISO Board also approved 36 additional transmission projects that it deemed necessary to making the state's grid more reliable. All told, the 41 transmission projects would cost around $1.7 billion dollars. Those costs could be covered by utility ratepayers.
"The CaISO is demonstrating California's global energy leadership by showing how a greener grid is as resilient and reliable as the grids of yesterday while paving the way for tomorrow's sustainable future and helping in the fight against climate change," said CaISO Board Chair Bob Foster in a press release. "A more diverse grid is a more energy secure grid."

[Note: A previous version of this story wrongly reported that the 36 additional transmission projects were not yet approved. We regret the error.]

Support Provided By
Read More
A blonde woman wearing a light grey skirt suit stands with her back to the camera as she holds a sheet of paper and addresses a panel at the front of a courtroom

California Passed a Law To Stop 'Pay to Play' in Local Politics. After Two Years, Legislators Want to Gut It

California legislators who backed a 2022 law limiting businesses' and contractors' attempts to sway local elected officials with campaign contributions are now trying to water it down — with the support of developers and labor unions.
An oil pump painted white with red accents stands mid-pump on a dirt road under a blue, cloudy sky with a green, grassy slope in the background.

California’s First Carbon Capture Project: Vital Climate Tool or License to Pollute?

California’s first attempt to capture and sequester carbon involves California Resources Corp. collecting emissions at its Elk Hills Oil and Gas Field, and then inject the gases more than a mile deep into a depleted oil reservoir. The goal is to keep carbon underground and out of the atmosphere, where it traps heat and contributes to climate change. But some argue polluting industries need to cease altogether.
Gray industrial towers and stacks rise up from behind the pitched roofs of warehouse buildings against a gray-blue sky, with a row of yellow-gold barrels with black lids lined up in the foreground to the right of a portable toilet.

California Isn't on Track To Meet Its Climate Change Mandates. It's Not Even Close.

According to the annual California Green Innovation Index released by Next 10 last week, California is off track from meeting its climate goals for the year 2030, as well as reaching carbon neutrality by 2045.