Title

Feds Approve Condor-Deadly Wind Energy Project

condor-5-27-13-thumb-600x450-51779
California condor | Photo: Jesse Varner/Flickr/Creative Commons License

The Bureau of Land Management (BLM) has given the thumbs-up to a Kern County wind project that the U.S. Fish and Wildlife Service (FWS) says is likely to kill at least one California condor. The BLM's positive Record Of Decision for Terra-Gen's Alta East Wind Project on 2,592 acres of land near the town of Mojave was released Friday, leaving only the approval of a right-of-way before the project can begin construction.

Story continues below

As we reported here two weeks ago, FWS has estimated that the Alta East project may well kill a California condor at some point within its 30-year operating lifespan. The BLM's Record of Decision on Alta East includes FWS's formal Biological Opinion (BiOp) on the project, and the BiOp makes that assessment official:

If and when that expected fatality takes place, Terra-Gen and BLM will need to reconsult with FWS, which will reexamine whether continued operation of the project will pose a threat of extinction for the California condor. The project would immediately be restricted to night-time operation only during the course of that reconsultation. As condors are predominantly day fliers, that restriction would prevent most condor injuries.

The BiOp also covers potential impacts of Alta East on the Threatened desert tortoise -- FWS's allowed take is ten over the life of the project or two in a single year -- and the Endangered Bakersfield cactus, which will lose more than 300 acres of its habitat to construction.

In the BiOp, FWS uses bleak language to describe the overall outlook for condors with or without wind turbines in their habitat. ReWire found one passage especially interesting:

That would seem to contradict recent statements of FWS Director Dan Ashe, who was in the Los Angeles Times quoted as saying quite the opposite in his informal announcement of the BiOp earlier this month. "The good news is that we have an expanding population of condors, which are also expanding their range," Ashe said.

The answer to that contradiction is that FWS among other agencies and organizations has been releasing captive raised-condors to keep the population up. That reintroduction program has cost more than $30 million since 1987, or more than $75,000 per condor now alive.

In exchange for what is in effect a permit to kill a condor, Alta East's operator Terra-Gen is agreeing to build a warning system to detect the VHS transmitters some birds now wear, to phase that out within the next few years in favor of a system that will detect condors without transmitters, and to build an observation station that will be staffed during daylight hours by trained biologists who can distinguish condors from other large birds at a distance. If a condor approaches the site, the biologists will be able to order the turbines slowed so that their blade tips are traveling at a speed of around 3 mph.

The BiOp is mum on what happens if the biologists determine that it is "only" a federally protected golden eagle heading for the turbines, though the BLM's mitigation plan for the project does require Alta East to count eagle fatalities.

In its BiOp, FWS points out that Alta East is far from the only wind turbine project in the vicinity that poses a threat to condors, and says that the threat will only get worse.

Unsurprisingly, environmentalists aren't happy with the BLM's decision to approve the project. "This massive recovery effort has cost millions of dollars and been the life's work of many talented people," said Kelly Fuller, American Bird Conservancy's Wind Campaign Coordinator. But why should the privately funded zoos and other conservation groups that raise the majority of the money necessary for this work continue doing so when a condor's life can be thrown away with the stroke of a pen by the federal government?"

For ongoing environmental coverage in March 2017 and afterward, please visit our show Earth Focus, or browse Redefine for historic material.
KCET's award-winning environment news project Redefine ran from July 2012 through February 2017.

We are dedicated to providing you with articles like this one. Show your support with a tax-deductible contribution to KCET. After all, public media is meant for the public. It belongs to all of us.