xHgGrtG-show-poster2x3-aXpIxNN.png

Artbound

Start watching
Tending Nature poster 2021

Tending Nature

Start watching
IYhnPQZ-show-poster2x3-Ytk6YwX.png

Southland Sessions

Start watching
RYQ2PZQ-show-poster2x3-OGargou.jpg

Earth Focus

Start watching
5LQmQJY-show-poster2x3-MRWBpAK.jpg

Reporter Roundup

Start watching
E5VnHdZ-show-poster2x3-PrXshoo.png

City Rising

Start watching
QraE2nW-show-poster2x3-uY3aHve.jpg

Lost LA

Start watching
Member
Your donation supports our high-quality, inspiring and commercial-free programming.
Support Icon
Learn about the many ways to support KCET.
Support Icon
Contact our Leadership, Advancement and Special Events teams.

Ivanpah Solar 'Syncs' To Grid For First Time

Ivanpah_First_Sync-thumb-600x450-60404
The sync test at Unit 1 | Photo: NRG

In a test announced by NRG Energy Tuesday, the Ivanpah Solar Electric Generating System successfully delivered power to the grid for the first time. NRG says the "proof-of-concept" test confirms that the 377-megawatt solar power plant's Unit 1 is ready to start operation sometime this year.

"Given the magnitude and complexity of Ivanpah, it was very important that we successfully complete this milestone showing all systems were on track," said Tom Doyle, President of NRG Solar, in a press release.

NRG co-owns the Ivanpah project along with Google and the project's developer BrightSource Energy. The project is being built by Bechtel on more than 3,500 acres of public lands in the Mojave Desert, just downhill from the Mojave National Preserve.

The power generated during the "sync" test was delivered to the Northern California utility Pacific Gas & Electric (PG&E), which has agreed to buy all the power from the project's Units 1 and 3. Southern California Edison will buy power from Unit 2.

Units 2 and 3 are scheduled for similar sync tests later this year.

"This is yet another major milestone that we have successfully achieved as Ivanpah approaches completion," said BrightSource Executive Chairman David Ramm. "Ivanpah is the showcase project for BrightSource's power tower technology and technical expertise. Validation at this scale demonstrates the viability of our technology as BrightSource increases focus on international markets and applications for concentrating solar power."

Support Provided By
Support Provided By
Read More
un mazo de juez de madera

Justicia retrasada: tribunales abrumados por el atraso de la pandemia

Desde la manutención de los hijos hasta el fraude de seguros, los casos judiciales se retrasan en todo California. Solo la mitad de los casos civiles y penales se resolvieron el verano pasado en comparación con las cifras anteriores a la pandemia. “La justicia no se ha cerrado. La justicia se ha ralentizado”, según un grupo de abogados.
A gavel on a table

Justice Delayed: Courts Overwhelmed by Pandemic Backlog

From child support to insurance fraud, court cases are delayed throughout California. Only half as many civil and criminal cases were resolved last summer compared with pre-pandemic numbers. “Justice has not shut down. Justice has slowed down,” according to an attorneys’ group.
People pull up in their vehicles for Covid-19 vaccines in the parking lot of The Forum in Inglewood, California on January 19, 2021. | FREDERIC J. BROWN/AFP via Getty Images

L.A. County Expands COVID Vaccines to Residents 65 And Older

L.A. County began scheduling COVID-19 vaccination appointments for those aged 65 and older today, but limited supplies and uncertainty about future allocations has left the inoculation effort shrouded in doubt.